Find Bill
Find Your Legislator
Legislative Deadlines
RSS Feed Permanent URL -A +A

2017 Statute



Prev Article 6. - SURFACE-MINING LAND CONSERVATION AND RECLAMATIONNext


49-613.Same; reclamation of affected lands, when; extensions; inspections; approval; release of bond or security. (a) An operator shall reclaim affected lands within a period not to exceed three years after the filing of the report required under subsection (b) of K.S.A. 49-612 indicating the mining of any part of a site has been completed.

(b) For certain postmining land uses, such as a sanitary land fill, the director, with the approval of the commission, may allow an extended reclamation period.

(c) An operator, upon completion of any reclamation work required by K.S.A. 49-611, shall apply to the director in writing for approval of the work. The director, within a reasonable time as determined by the commission, shall inspect the completed reclamation work. Upon determination by the director that the operator has satisfactorily completed all required reclamation work on the land included in the application, the commission shall release the bond or security on the reclaimed land, shall remove the land from registration, and shall terminate or amend as necessary the operator's authorization to conduct surface mining on the site.

(d) Periodic inspections may be conducted by the director or the director's designee, to ensure that the operator is following the reclamation plan.

History: L. 1994, ch. 197, § 13; July 1.



Prev Article 6. - SURFACE-MINING LAND CONSERVATION AND RECLAMATIONNext